Owner-furnished equipment is arriving. Who receives it at the industrial building?

By

Updated

Original Spanish article: November 23, 2026.

Aerial view of DINUTRI during construction, from Grupo COB’s project portfolio.

The bid lists an air-conditioning unit as “owner-furnished.” Purchasing has issued the order. The site superintendent still has a question: when the truck reaches the gate, who takes the unit from there?

A purchase order settles who buys the equipment. The construction team also needs to agree on who receives it, moves it into position and connects it. The best time to have that conversation is while the bids are still open.

Follow one item from the truck to its final position

Pick a specific unit and ask the vendor where its delivery ends. Compare that answer with the contractor’s bid. Give unloading, moving the unit into the building and setting it on its base a line each. A blank is worth resolving before a driver is waiting at the gate.

Agree on what the receiving team will check. The delivery slip identifies what arrived. The approved drawing gives the team a reference for the model expected. If the casing is dented or the model number differs, someone needs to document the discrepancy and reach the person authorized to decide what happens next.

Ask both bidders the same question

One contractor might include setting the unit on its base and exclude connecting it. Another might price the connection and assume the unit is already in place. A lower total tells the owner little until both bidders are pricing the same work.

Ask each bidder to identify inclusions, exclusions and the information needed for a firm price. Look for gaps and overlaps. If a decision depends on the tenant, record who can make it and when a delay would start to affect the site team.

Put the agreement on the schedule

Link the delivery date to a condition the site team can check. The delivery route must be available, for example, and there must be an agreed place to receive the unit. If the tenant places the order, agree on who will share vendor updates and who will review any change to the arrival date.

Try a simple question at the scope meeting. “If this unit arrives on Tuesday, who signs for it and how far do they take it?” When purchasing, construction and operations give the same answer, the owner has a much clearer basis for comparing bids.

See Grupo COB’s construction services to discuss which parts of your project need to be included in the bid.

Ready to start your project?

Contact us for a personalized quote. Our team of experts is ready to help.

Request a Quote